Projects & Case Studies
Project #3
American Automotive Company, Windsor, ON
2001/2002
- The Hybrid CHR-FLUE™ system, was installed for combined APC (PM) and HR from the exhaust gasses emitted by the iron castings operation Cupola process.
- The new Hybrid CHR-FLUE™ was to recover 37 mmBtu/hr, and replace the existing Venturi scrubber for particulate removal – thereby reducing 1,000 HP of electrical power consumption
- The recovered heat would be used to supply continuous glycol heating to the fresh air make-up HVAC systems of the Truck Engine Plant.
- Financial payback was projected at 3.5 years (in 2001); however, was slightly longer at 4.5 years due to Cupola process & automotive production changes. However, based upon todays 2 x higher energy unit costs, the payback would be less than 3.0 years.
- This CHR-FLUE™ installation was to reduce the client’s fossil fuel purchases in excess of $1 million annually. The reduced fuel consumption also eliminated the discharge of more than: 35 metric tons of Nitrogen Oxides (NOx) and more than 15,000 metric tons of Carbon Dioxide (CO2) each year
Econolibrium Projects & Case Studies
The following projects and case studies demonstrate Econolibrium’s leadership role as the premiere CHP/Co-(Tri-)generation solutions + Condensing Heat Recovery solutions provider in Ontario for Hospitals, Public Facilities, Commercial Facilities, and Industrial Facilities Projects.
HOSPITALS AND HEALTH CARE FACILITIES
Reference Projects:
• Project #1:
Saint Vincent Hospital
Video Interview – Réjean Proulx, Manager of Heat and Power Plants
• Project #2:
Royal Ottawa Hospital
• Project #3:
Gatineau Hospital
• Project #4:
Stratford General Hospital
• Project #5:
Grand River Hospital
• Project #6:
Ottawa Civic Hospital
• Project #7:
Tillsonburg District Memorial Hospital